Laboratory Equipment

LABNEWS Banner

Facebook  YouTube  Twitter 

 


Site Sponser






Home > Markets > Laboratory Design & Furnishings

Read/Post Comments

Renovation Revisited

Five ways of rethinking renovation can lead to faster, greener and less-expensive results.

by Mark Reed, AIA, LEED AP, and Erik Mollo-Christensen, AIA

Renovation schedule for the Searle Chemistry Laboratory at the Univ. of Chicago.
Figure 1. Renovation schedule for the Searle Chemistry Laboratory at the Univ. of Chicago.
Click here to enlarge.
Many science building owners and institutions reject full-building renovation options because they consider it to be just as expensive, if not more than, as new construction and logistically more challenging. The challenge of trying to phase a renovation without disrupting research often overwhelms even the most seasoned facilities professionals.

However, leading institutions such as Brown Univ. and the Univ. of Chicago have discovered that if a project can be crafted and staged to eliminate unnecessary cost and complexity, renovation becomes not just an option but almost an obligation. When it comes to speed, sustainability, and cost savings, renovation can be the best way out of a facilities jam.

Don’t pay people to sit around

On a recent bid summary, the General Conditions for a 100,000-ft2 science project totaled $200,000 per month. Most of this $4.8 million expense covered the salaries and benefits of project managers, field engineers and other onsite staff, as well as the cost of the trailers, office equipment and utilities required to support them for 2 years.


On a phased renovation project, this expenditure can extend months longer than on new construction, contributing to the commonly held notion that renovation is more expensive than new construction. But if a renovation project can be done in a single phase, the same logic works to the project’s benefit. By taking advantage of the existing structure and envelope and eliminating the need to prep the site, lay foundations, and erect the superstructure and enclosure, an institution can save 9 to 12 months with a single-phase renovation versus a new construction project. This shortened schedule could cut the General Conditions in half and yield a $2 million savings in salaries and trailer rental costs alone (Figure 1).

Getting to a single-phase renovation

A phased renovation adds millions of dollars to a budget but adds no value to the completed project. These millions come from the extended General Conditions and from the cost of creating temporary measures to ensure life safety, access and continuity of services to the occupied areas. In this context, it is worth spending $1 million to $2 million on swing space to save $7 million to $8 million on the actual project. At first glance, swing space can be hard to find, so a creative and flexible approach is needed:

• Don’t expect the swing space to be ideal. Be prepared to accept loss of contiguity and adjacency for a finite, short period of time.

• Don’t expect the swing space to be the perfect size. Compression often is a necessary compromise.

Convert under-utilized spaces to swing space. Library stacks within lab buildings and semester-dependent teaching labs often can be consolidated to free up space.

Time your renovation to coincide with the end of new construction projects for optimal swing space opportunity.

Consider leasing space from local companies or adjacent institutions.

Don’t rule out the possibility of taking space from other departments and divisions.

There’s gold in them thar walls

Needed chemistry lab renovations also offered an opportunity to correct circulation issues at the Univ. of Chicago.
Figure 2. Needed chemistry lab renovations also offered an opportunity to correct circulation issues at the Univ. of Chicago.
Click here to enlarge.
In addition to time savings, infrastructure already in place offers real value whereas site development, foundations, structure and exterior skin in new construction have a combined value of approximately $100/sf. By viewing existing infrastructure as valuable rather than obsolete, a creative owner can revive a building for a second life at a more reasonable cost than that of a new construction project.

The Univ. of Chicago made this realization when deciding to renovate its Searle Chemistry Laboratory, a 90,000-ft2 building from the late 1960s. The university determined that a shorter schedule—made possible by swing space opportunities and the latent value of the building’s limestone exterior and concrete structure—could yield a faster result at a fraction of the cost of a new building (15 months/$32 million verse an estimated 24 months/$50 million).

Critical to the cost savings was a $1 million compression and relocation project for three faculty members and for core instrumentation that allowed a single phase of renovation. Through a temporary compression strategy applied to the chemistry faculty, one member was accommodated nearby in the recently completed Gordon Center for Integrated Sciences. The other two investigators and the core instrumentation suite of mass spec, X-ray diffraction and NMR were accommodated in renovations to the adjacent Jones Laboratory (Figure 2).

One of the problems inherent to the original Searle envelope design was that it formed a 200-ft barrier between the traditional quadrangles and the westward expansion of the campus. A new pass-through entry need to be introduced into the midblock of the building, creating a major campus connection from east to west. While preserving the majority of the envelope, the design team also trained a critical eye on the inadequacies of the original building. Using renovation to correct the shortcomings of a previous era’s poor planning is an effective technique for enhancing broader campus design issues.

Turn constraints into assets

Another technique employed by the Univ. of Chicago was to take advantage of existing constraints. The electrical system of the building provided one such opportunity. An existing electrical vault in an adjacent building fed the Searle Building and had a limited amount of capacity. Rather implementing a full electrical service upgrade, the design engineer identified a set amount of power capacity for plug load once the MEP core load was established. The architects then worked with the user group to ensure the equipment and plug layouts in the lab fit within the limitation. This reverse-engineering avoided an expense that would ordinarily be required with a less-thorough need analysis.

A section diagram of the Brown Univ. adaptive reuse project shows zoning of capabilities.
Figure 3. A section diagram of the Brown Univ. adaptive reuse project shows zoning of capabilities.
Click here to enlarge.
Get into the zone

Most renovation projects involve sub-optimal buildings with numerous deficiencies and do not have the flexibility of contemporary lab design. By identifying the zones of capability and locating functions appropriately, institutions can work with what they have rather than spend time and money creating new, perfect locations.

Not long ago, Brown Univ. had a pressing need for laboratory space due to ongoing delays with a large project and had acquired a former jewelry manufacturing building off-campus. The building had been recently renovated for office use but had a mixture of structural systems, irregular floor heights, non-orthogonal column grids, and small floor plates. The program included biomedical labs, chemistry and analytical labs including a 600-mHz NMR, and a vivarium, as well as an aggressive schedule and budget, for which Brown chose a design/build delivery method.

The design approach provides several useful lessons in the way that it defined the following zones of capability:

• Find a small zone of stable space for critical instrumentation. NMRs, microscopy and other vibration-sensitive devices usually work well at ground level; if there is high-bay space in an annex, installation and gauss fields are easier as well (Figure 3).

In an adaptive reuse project where existing conditions are less than ideal, placing offices in unusual or constrained spaces is often the best strategy.
Figure 4. In an adaptive reuse project where existing conditions are less than ideal, placing offices in unusual or constrained spaces is often the best strategy, preserving more open, accessible spaces for labs.
Click here to enlarge.
• Locate the vivarium in a secure zone. A basement or non-ground floor location is best; one floor away from the loading dock minimizes the cost of a dedicated elevator and shortens the material path. Because vivarium rooms are generally small, the layout challenges of a non-optimal column grid usually are not the determining factor.

• Don’t expect lab bench spacing to be perfect. Locate the bench/table zone to achieve the longest run of space for flexibility, and avoid an idiosyncratic central core.

• Be opportunistic with office locations. Many renovated buildings have unusual corners, constrained grids, or smaller spaces in central cores that are best suited for offices, so don’t spend renovation dollars creating ideal offices within lab zones (Figure 4).

Conclusion

In conclusion, when selling a renovation idea to colleagues who may be skeptical, keep in mind the following points:
• Plan on spending money and time on swing space to achieve a single-phase project.
• Remember that the work spent on creating swing space has retained value beyond the project duration.
• Assume a 9- to 12-month time savings over new construction. Calculate both General Conditions savings and reduced escalation costs.
• Develop a realistic budget that includes contingencies for time as well as cost, and develop a schedule with specific milestones to avoid extended work.
• Calculate the value of work-in-place that will be retained.
• Be creative about matching your program to the unique qualities of your building.
• Use the renovation to repair damage caused by poor planning from the past. Open up new connections, and create stronger relationships between the building and the site.
• Don’t force the program where it doesn’t fit.
• Renovation is inherently more sustainable than new construction.

Mark Reed is a principal/VP and Erik Mollo-Christensen is a principal with Tsoi/Kobus & Associates, an architecture, planning and interior design firm located in Cambridge, Mass. (www.tka-architects.com).

This article first appeared in the October issue of Lab Design Newsletter.


Contact Editor Print Article Email To Friend

Comments
Type Your Comment...
Name:   
E-mail (optional) *E-mail addresses do not publish to the site.
Comment:   


Editor's Corner

Tim Studt, Editor-in-Chief
Tim Studt
Editor in Chief

Statistical Sampling Could Protect Food Safety
The current recall of hundreds of millions of eggs based on a couple of hundred cases of salmonella poisoning (none fatal) reflects on the statistical sampling methods in place to protect the public’s safety.. ...continue

Application Notes
More

Most Viewed Content
Advantage Business Media © Copyright 2010 Advantage Business Media
Privacy Policy |  Terms & Conditions |  Advertise with Us